Quick Facts

VIPER

  1. 241 total sites planned for statewide coverage.
    • 222 sites constructed and on-the-air
    • 6 sites are fully funded and under construction 
    • Funding for remaining site construction is ongoing
       
  2. VIPER is 92% complete (number of sites) with 222 sites on the air
     
  3. 109,817 total users (consoles not included) are currently on the network
     
  4. South Carolina has the same type Interoperable System; N.C./S.C. can talk to each other using the same type user device.

Critical Issues

  1. Lack of exemption for State owned property has now become a significant challenge to construction since local government are now able to veto the State’s use of its own land.
     
  2. In moving forward with construction of new tower sites, the challenge will be to get fully executed leases prior to site construction.
     
  3. VIPER Infrastructure Implementation costs
     
    • $202.5M funded to date (includes $7M Recurring for tower construction in FY18-19)
       
  4. VIPER Operation and Maintenance Costs
     
    • Current funding is $7M Recurring